RECEIVING AND DISPATCHING OF GOODS
Maritime receiving and dispatching of goods
- vessels with a maximum dead-weight up to 30,000 t and maximum draught of 14 m
- flexible connecting pipes Ø 150 with ANSI 150 LB flanges
- transport pipeline system Ø 150/200/250 (unheated, uninsulated iron) connecting the terminal pier with the terminal tanks
- compressed air or nitrogen pipeline cleaning with polyurethane cushions (pigging)
RECEIVING CAPACITY BY VESSEL:
70 m³/h– 200 m³/h
Receiving and dispatching of goods by railway
- four- and two-axle tank cars with side or top loading/unloading
- four reloading stations with separated pipelines on two proper industrial railway gauges
- pipeline cleaning with water and ecological detergent and compressed air or nitrogen pipeline cleaning (pigging)
70 m³/h – 200 m³/h
Receiving and dispatching of goods by tank truck
- side and top loading/unloading
- four reloading stations with separated pipelines
- pipeline cleaning with water and ecological detergent and compressed air or nitrogen pipeline cleaning (pigging)
15 m³/h
30 m³/h
THE RELOADING CAPACITIES
The reloading capacities are based on:
- viscosity of goods
- nominal connection openings:
- vessel: NO 150, NO 200
- railway: NO 100
- tank truck: NO 80
WORKING HOURS
DISPATCHING GOODS:
- BY VESSEL: 24 hours a day including Sundays and holidays
- BY RAILWAY: 7 AM – 10 PM every working day
- BY TANK TRUCK: 7 AM – 10 PM every working day
RECEIVING GOODS:
- BY VESSEL: 24 hours a day including Sundays and holidays
- BY RAILWAY: 7 AM – 10 PM every working day
- BY TANK TRUCK: 7 AM – 10 PM every working day